SpaceDIRT Q4 2026 Update

Founder and CEO Shaun Riddell presented our first quarterly update to the company. We are starting these updates to show you what we are doing at SpaceDIRT, the progress we make each quarter, and where we are headed.

Our mission is to build infrastructure using robots. We believe the future of development, on Earth and in space, will be heavily influenced by robotics, and we are working along a structured path to get there.

The quarter in numbers

  • 9,969 m driven hands-free, over 93 laps of our yard
  • Two SLED75 rovers built
  • An Arctic test chamber rated to −75 °C, built and commissioned in house
  • A $500K Canadian Space Agency study under way

Three business units

The company runs as three teams. Platform owns the SLED75 and the upcoming SLED150-M, and keeps its focus on one thing: a robust, reliable, cost-effective platform that serves many payloads and many customers. Payload builds the equipment that rides on the platform and sets the interface the platform has to meet. Space Systems carries our work with the Canadian Space Agency and looks at what comes next.

SLED75

Both SLED75 rovers are engineering complete on their mechanical drivelines and control system design. The work now is the autonomy kit: we are trying different sensors and configurations to reach a higher level of autonomy while keeping a high level of safety.

Safety starts before every test. One rover drives the edge of the test area and logs it as a GPS perimeter. If a rover leaves that perimeter during waypoint testing, it shuts down immediately. Our ground control radio sends commands at 50 Hz with a 10 ms median round trip, and carries a live video stream, telemetry and safety checks.

Arctic test chamber

We built an 8 cu ft chamber that tests components down to −75 °C, so we can validate the systems that will go into Arctic units. The first test, on 29 October, was a planetary gearbox, and it gave us a complete picture of how heat moves during the test and how that carries over to the real world.

SLED002

SLED002 went from components to a working prototype in five business days. SLED001 took much longer. Every build matures the way we bring up new units, so a problem we solve once stays solved. For the SLED150-M we are targeting two business days from parts in the shop to a working prototype.

SLED150-M

The SLED150-M is our first militarized platform, built to carry 200 kg and tow 500 kg. It is designed for reliability and manufacturability: off-the-shelf automotive components for most of the driveline and a simple welded chassis. That keeps it cost competitive and gives the field repairability and configurability the military requires.

Payload

The payload team is in a phase of rapid development. Alongside our fielded drill, SLED001 will receive a front loader and a rototiller, and SLED002 a dump bed. We plan to build all three before the end of the year. This work defines the interface the platform has to meet and shows customers what a SLED can do.

Space Systems

We continue our $500K Canadian Space Agency study of in-situ resource utilization (ISRU) architecture, awarded in June 2026, and will deliver the draft study to the CSA by the end of the year.

We also asked how a SLED would work on the Moon, and one idea stood out: a lunar garage. Inside it, crews work in shirt sleeves on prototype equipment, build it on top of a SLED, send it out to test, bring it back and change it again. That shortens the development cycle. It is exactly what we do in our own garage, and we think it is key to developing space faster.

2027

  • Q1: Design closed, four engineers hired
  • Q2: Pre-production units in customer demos
  • Q3: Certification and design for manufacturing
  • Q4: First production order: 20 vehicles

Thank you for following along. We look forward to the next update.